Featured Projects

Baseline Avenue Storm Drain Improvements - Citrus to Sierra

This Project is a City of Fontana Capital Improvement Project which completes the last segment of Storm Drain and widening of Baseline Avenue within the City limits. Riverside Construction Company, Inc. started this Project in the Summer of 2008 and with various Utility conflicts, the project is projected to be complete by the end of January 2010. This Project consisted of various Storm Drain systems including 2,698 LF of Double 9’x8’ Pre-Cast box later followed by 2,323 LF of Double 8’x8’ Pre-Cast Box for a Project Bid amount of $11,347,891. At this point of December 2009, all of the main components of the project have been completed and we are nearing a successful completion with Landscaping currently underway. We are anticipating final Paving to be complete by the end of January 2010.

Original Contract Amount: $ 11,347,891.00

Subcontractors: Amber Steel (Reinforcement), Cal Stripe (Striping), Matich Corporation (Paving), Marina Landscape (Landscape), VT Electric (Electrical), SRD Construction (Sewer), Area West Fence (Fencing) and Granstrom Masonry (Block walls/Masonry).

Suppliers: Rialto Concrete Pipe (RCP and Pre-Cast Box), Mission Redimix (Concrete), Alhambra Foundry (Misc Iron & Steel).

Owner: City of Fontana

Inspection: City of Fontana

Design: Berryman & Henigar

Project Management: Carl Short

Project Superintendent: Tom Gutzwiller

Ramona Avenue Grade Separation

Riverside Construction Company, Inc. has completed all underground storm drain, water and sewer on the project and we continue to move forward with Bridge progress. On December 1, 2009 we reached our milestone of placing concrete in our soffit and stems for the Bridge. The Bridge work continues with the added SCE utility. Bridge deck pour anticipated at the end of December to complete the Bridge Structure. Landscape work to commence shortly following the SCE work that was added to the contract for North to South utility access. Project completion projected for the end of May to early June of 2010.

Original Contract Amount: $8,200,000.00

Owner: City of Montclair

Inspection: Caltrop

Designer: LD King

Project Management: Carl Short

Project Superintendent: Shelby Mongeon

Subcontractors: Avar (Pre-Stressing), Area West Fence (Fence & Gates), CP Construction (Water & Sewer), Calmex Eng. (Asphalt Paving), ACL (Barrier), Foundation Pile (Piling), Steiny & Company (Electrical), Marina Landscape (Landscape), American Steel Placers (Reinforcement) and Sudhakar Int. (Striping).

Suppliers: Long Beach Iron Works (Misc Iron & Steel), Windrow Materials (Aggregate Base), Robertsons (Concrete), Scougal (Bearing Pads), Rialto Concrete Products (RCP) Reinforced Earth Products (MSE Wall Panels) and Champion Lumber, Squires, Van Matre (Lumber Materials).

 

 

Cypress Avenue Overcrossing

Riverside Construction Company, Inc. commenced work on the Cypress Avenue Overcrossing project in May of 2009. This project mainly consists of the Construction of a Bridge Overcrossing the I-10 Freeway that will facilitate traffic from Valley (North) to Slover (South). The Bridge consists of over 100,000 Cubic Yards of Import dirt material, 1,000,000 pounds of reinforcement and 3,200 Cubic yards of concrete in the Bridge itself. This project also consists of various storm drain systems including the removal of a portion of the trapezoidal channel, and the Construction of a vertical wall channel to facilitate Bent 4 of the Bridge. The projected completion date for this projectis in the latter part of 2010.   

The current status of the project is the Bridge Construction. The Soffit and Stem Reinforcement has commenced with and approximate concrete placement date for the Soffit & Stems in the latter part of January 2010.

Original Contract Amount: $10,527,904.00

Owner: City of Fontana

Construction Mgmnt/Inspection: AECom/LAN Engineering

Designer: Parsons

Project Management: Carl Short

Project Superintendent: Mike McDonagh

Subcontractors: Ace Fence Company (Fencing), Cal Stripe, Inc. (Striping), Competitive Edge Electric (Electrical), CTM Construction (Barrier Rail), Dywidag Systems, Foundation Pile, Inc.(Piling)

JV Landclearing (Clear & Grubb), Marina Landscape (Landscape), Matich Corporation (Aphalt Paving), Ulmer Industries (Sign Structures), United Steel Placers (Reinforcement).

 

Suppliers: Rialto Concrete Pipe (Storm Drain Pipe), Robertsons (Concrete), Scougal Rubber (Bearing Pads), Watson Bowman (Joint Seal Assembly), Titan Materials (Class II Base), Long Beach Iron Works (Misc Iron & Steel and Bridge Metals), Windrow Materials (Import) and Champion Lumber, Squires and Van Matre (Lumber Materials).